Question 1

The Scrum Master observes the Product Owner struggling with ordering the Product Backlog. What is an appropriate action for the Scrum Master to take?
(Choose the best answer.)


  1. Suggest the Product Owner extend the Sprint, so he can have more time to order the Product Backlog.
  2. Suggest that the Development Team does the ordering to be sure that it is a feasible ordering of work.
  3. Offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize value.
  4. Present the Product Owner with an ordered Product Backlog to use.
  5. Encourage the Product Owner to work with the Development Team to see which items technically are fastest to implement.
Correct answer: B



Question 2

True or False: The Product Owner makes sure the Developers select enough from the Product Backlog tor a Sprint to satisfy the stakeholders.


  1. True
  2. False
Correct answer: B
Explanation:
According to the Scrum Guide, the Product Owner does not make sure that the Developers select enough from the Product Backlog for a Sprint to satisfy the stakeholders. The Developers are responsible for selecting how much work they can do in a Sprint, based on their capacity and past performance. The Product Owner may influence them by ordering and clarifying the Product Backlog items, but does not control their selection.
According to the Scrum Guide, the Product Owner does not make sure that the Developers select enough from the Product Backlog for a Sprint to satisfy the stakeholders. The Developers are responsible for selecting how much work they can do in a Sprint, based on their capacity and past performance. The Product Owner may influence them by ordering and clarifying the Product Backlog items, but does not control their selection.



Question 3

Who is responsible for collaboration with stakeholders?
(choose the best answer)


  1. The Business Analyst.
  2. The Scrum Team.
  3. The Team Manager.
  4. The Project Manager.
  5. The Developers.
Correct answer: B